Thank you for the enquiry, we will need the information below to assist with a specification for these steels, please send the information to [email protected]

  • Level of fire protection required (i.e. 30, 60, 90min, etc.)
    - Each steel section dimension (i.e. 254x146x37 UB)
    - Quantity and length of each section (or overall meterage for each section)
    - Orientation (horizontal or vertical)
    - Number of sides to be painted (all sides, 3 sides, 1 flange, etc.)
    - Structural Steel Design Code (i.e. EuroCode, BS5950, BS476; Part 21, etc.)
    - Building type (i.e. office, domestic, storage, etc.)
    - Environment (internal, external, car park, chemical exposure, etc.)
    - Application on site or in shop

  • Alternatively you can just forward us drawings, fabrication/cutting lists and we'll extract the information from them but in that instance we'd need some guidance as to what to allow for i.e. all steels on first floor, etc.